Photo courtesy of the University of Rochester
In a joint effort by the University of Rochester and Rochester, New York-based Turner Pike Construction, a vast majority of waste produced by the large-scale demolition of buildings surrounding the Strong Memorial Hospital’s Emergency Department has been recycled or diverted from landfill.
“The methodical demolition is quite meticulous,” says Robert Maloney, project coordinator for the university's Department of Planning & Project Management. “Each wire, pipe and conduit had to be carefully removed.”
After waste is divided into piles, a large magnet passes over them to remove any remaining metal. Out of 340 tons of construction waste, 301 tons (just over 88 percent) have been recycled to date. Much more material is expected to follow suit as work continues, the university says.
At the beginning of the year, the project team aimed to divert at least 50 percent of construction and demolition waste, including concrete, steel, copper and wood.
Materials not recycled include asbestos-containing material (all of which was removed before demolition began), some plastics and other scraps that can’t be reused. Concrete is ground down to pebble-size material and used to make roads or pavers sold in home and garden stores. Steel is recycled in the scrap metal market. Much of our non-recyclable material will go to the High Acres Landfill in Fairport, New York.
Transformers that were once used in the now-gone transformer building were shipped, fully intact, overseas where they will be used in India.
This cleanup comes before the digging of the building foundation, which will be followed by mass excavation later this year. Given this is the university’s largest project ever, Maloney says this is a good opportunity to prioritize diversion.
“This is good for all of us,” Maloney says. “It means some cost reduction, but we’re also trying to build in a smart and sustainable way for future generations.”
Latest from Construction & Demolition Recycling
- Pacific Steel selects Danieli as EAF equipment supplier
- Viably, Turmec partner on Ohio installation
- EPA plans to revisit numerous environmental, climate regulations
- Fornnax wins Green Innovation of the Year award
- ABC: Construction backlog inches lower, staffing levels expected to grow
- Former detention center in Cleveland set for demolition
- Ferrous market upward price momentum continues into March
- Build Reuse joins up for Circularity event