While San Francisco’s Candlestick Park may be no longer, Candlestick Point, the land for which the stadium got its name, is still there and is getting a major makeover. Miami-based developer Lennar Urban has plans to convert Candlestick Point adjacent Hunters Point Shipyard into 700 acres of mixed-use buildings, shopping centers and much-needed housing. But before stores and houses could go up, the stadium, which housed thousands of San Francisco 49ers and San Francisco Giants fans over the years, had to come down.
Demolishing Candlestick Park proved to be a unique challenge for Oakland, California’s Silverado Contractors Inc. due to its sheer size, reinforced-concrete wind baffle and thick concrete walls — all features that contributed to the massive responsibilities it once held. Candlestick Park stadium opened as a ballpark in 1960 after the New York Giants moved to San Francisco, and it was converted into a football stadium during the 1970s. The stadium housed nearly 70,000 fans during a big game, prevented gusts of wind from blowing field goals and extra points astray, and withstood years of earthquakes, including one measuring 7.1 on the Richter scale in 1989.
It was a 132-foot-tall, 630,000-square-foot layer cake of about 96,000 tons of reinforced concrete and steel. The original plan detailed imploding the stadium; however, the developer and Silverado had to consider the Bay Area Air Quality Management District’s dust exposure requirements and noise concerns from the surrounding neighborhood. That changed the plan, and using excavators fitted with hydraulic attachments became the best solution.
“We’ve done some selective demolition of other stadiums in the past, but this is the first time we’ve ever demolished an entire stadium,” says Andrew Baird, Silverado Contractors project manager.
The demolition contractor based in Oakland, California—just across San Francisco Bay—tackles a wide range of projects, from selective demolition to complete building and bridge removal, primarily on the West Coast.
“Taking down the structure piece by piece, one section at a time was the only way we could ensure the safety of crews during demolition while minimizing dust,” Baird says. It also was a rare opportunity not many contractors get to experience—the complete demolition of a stadium, which hasn’t occurred on the West Coast since Seattle’s Kingdome demolition about 15 years ago.
Tackling the project
But in November 2014, the memory of that project would take a back seat to what was in store for the Candlestick Park stadium. Silverado began the demolition of the stadium by stripping out all 68,500 seats and performing hazardous material abatement, a feat that took several months.
By February 2015, Silverado was ready for the next phase of the project: demolition. About 30 laborers stripped and gutted all nonrecycleable debris from concession stands, bathrooms and luxury suites. When spring came it was time to bring out the heavy hitters: a team of Silverado equipment operators and several hydraulic attachments, including Atlas Copco breakers. They were ready to face heavy demolition, starting with the stadium’s main structure.
“It’s a fairly challenging project because it’s such a big structure and very different from a typical building,” Baird says. “But after reviewing structural elevations and breaking into it, you realize it’s like any other building, just on a much larger scale.”
Before the hard-hitting demolition could begin, Silverado had to ensure everything was in position. Operators using an excavator fitted with a hydraulic shear attachment cut out the steel retractable bleachers, giving the crew access to the field for sorting rubble.
Cutting through the steel sections was considerably faster than breaking through a concrete area. It meant they could get onto the field and in position faster, which is why it was a good starting point for Silverado’s crew.
Once the crew was in formation, it was time to tackle the stadium’s concrete wind baffle and upper deck as well as its lower reserved seating and boxes. The team of operators used a wide range of equipment and attachments, including aerial lifts, excavators, hydraulic breaker attachments, shears and water sprayers. The play: demolish from top to bottom and clockwise from the stadium’s southwest corner.
Up to bat
“We chose Atlas Copco breakers because they’re a proven product, are simple to maintain and have fantastic hitting power,” says Sean Holifield, Silverado Contractors operations manager.
Excavators fitted with Atlas Copco HB 2500 and HB 5800 breaker attachments smashed reinforced concrete walls, while another excavator with a hydraulic shear attachment cut rebar and steel supports as they emerged from the crumbling concrete.
“We used those breakers nearly all day, every day and with minimal downtime,” Holifield says.
Both breakers feature Atlas Copco’s ContiLube II lubrication system, which automatically greased wear bushings to minimize wear and virtually eliminate downtime from manual greasing.
“Productivity is critical in this industry,” says Dana Creekmore, Atlas Copco regional channel manager, west. “And much of that productivity boils down to your equipment, from using breakers that require minimal maintenance to simply having the right attachment for the job.”
The threat of downtime was minimized, but the risk of dust was an ongoing concern, particularly on one of the highest points of the project—the wind baffle.
“It sat about 120 feet off the ground, and it could have been quite a logistical challenge to get the breakers in there as well as water to suppress the dust at the right points,” Holifield says. “It would have been fast and easy to knock it down with a ball and crane, but the amount of dust and debris would have been a huge concern.”
Manually spraying water on the points of impact and debris drop zones would be nearly impossible with a wrecking ball because of its inaccuracy. Using handheld breakers would have been more precise, but put operators in harm’s way. The stadium’s walls were as thick as 18 inches and needed heavy-hitting power to come down.
“Dust control was a major concern not only on the wind baffle, but nearly the entire project. And we had to tackle it on two fronts—at the point where we were breaking material and where it hit the ground,” Baird says.
Silverado attached spray nozzles to the excavators, which automatically released water to control dust at the tip of the breaker. This ensured excavator operators had a clear view of the work and eliminated the need for manual dust control, which meant crews could remain a safe distance away from any falling debris. Silverado also had operators controlling nozzles on aerial lifts that were set farther back than the excavator, spraying the point where debris hit the ground.
For the wind baffle, Silverado called in its high-reach, 76-ton excavator and Atlas Copco’s HB 2500 hydraulic breaker. The excavator’s boom could reach as high as 130 feet, putting the baffle within the breaker’s striking distance and the operator out of range of falling debris. Outside the stadium, the operator pushed the breaker’s chisel against the baffle’s curved concrete wall and perforated it. With an impact rate of 580 blows per minute, it didn’t take long to knock out chunks of concrete and rebar, causing the baffle to sag then collapse onto the upper deck.
“Without the breaker attachment, we would have had a real difficult time breaking down that wind baffle while suppressing dust. It would be nearly impossible to get the same control with a ball-and-crane,” Baird says.
Winning team
While work was going on above, an operator using another 76-ton excavator and Atlas Copco’s HB 5800 breaker delivered as many as 480 blows per minute to tackle the thick reinforced concrete walls below. They teamed with another excavator operator who was using shears to take out lower seating sections, which also were made of reinforced concrete.
“Watching the large breaker work in conjunction with the shear attachment is fairly amazing because what they accomplish together is much more than what any one machine can do on its own,” Baird says.
The breaker smashed through external concrete walls and pillars, while the other excavator reached in with its shears and removed the mangled pieces of rebar and steel sheets from the upper deck area.
“Not only was it less hassle to have two excavators, but it also was more efficient,” Baird says.
Because each excavator was equipped with its own attachment—one for breaking and one for cutting—the crew didn’t have to stop and switch attachments. They demolished the area from the baffle’s peak to the last row, one section at a time, in just hours.
As each section came down, another crew moved in to sort rubble. They used an excavator with a bucket to separate twisted rebar from the concrete, and they stockpiled it on-site before crushing it for backfill on the new site or recycling for road building. The crew also sorted and shipped stockpiled rebar and nonferrous metal for recycling. In all, about 98 percent of the rubble from the stadium was recycled.
“This project required a lot of teamwork at every level to allow our highly skilled operators to succeed,” Holifield says. “From our superintendent, Oscar Reyes, overseeing our entire workforce, Andrew Baird coordinating them and their equipment, and the reliable customer support from Atlas Copco’s Dana Creekmore, it ensured that we were always pushing forward.”
Before finishing demolition in late August, Silverado’s crew continued to rely on Atlas Copco breaker attachments to demolish the remaining concrete slabs. They even brought in reinforcements—the HB 4700 and HB 3100 breakers.
It’s true with football and sometimes it’s true with stadiums: what goes up, must come down. And oftentimes, including the Candlestick Park stadium demolition, gravity is the enemy—from kicking up dust as debris hits the ground to eliminating a fast and easy way to demolish, such as imploding.
But there’s always a victor who masters the challenge. Just like a winning drive that scores a touchdown, Silverado Contractors ran a flawless offense against dust generation and downtime, which ultimately won them the game of safe and efficient demolition.
This article was submitted on behalf of Atlas Copco, based in Stockholm, Sweden. More information is available at www.atlascopco.us.
Explore the November 2015 Issue
Check out more from this issue and find your next story to read.