Alabama DOT crews continue bridge demolition

Demolition slated to take place June 15 and 17.


The Alabama Department of Transportation (ALDOT) crews will continue to demolish the B.B. Comer Bridge over two more days, a report by Waay TV says. The dates are 9 a.m. on Wednesday, June 15 and Friday, June 17.

These dates were in addition to the demolition scheduled to take place June 8 at 9 a.m., the report says. According to ALDOT, there will be more blasting dates announced as demolition continues.
 
All highway and river traffic within a 1,500-foot radius will be stopped before the blasting begins. According to the report, ALDOT estimates traffic on Alabama 35 and Alabama 40 at Alabama 35 will be stopped for 15-20 minutes, beginning shortly after 9 a.m. The agency said river traffic can expect a longer wait.
 
ALDOT advises motorists to use alternate routes or expect delays.