A local media report indicates a city in Ohio will pay less than expected to demolish a bridge, thanks to the steel content of the aging structure combined with a high-value ferrous scrap market.
A late March online report from the Youngstown Vindicator in Ohio says the three bids that city received to demolish a bridge over an abandoned railroad right of way were “significantly less than the city’s estimate” for the project.
A deputy director of public works quoted by the newspaper said, “There’s so much steel on the bridge, which was a factor in the estimate being high. We’re conservative with the salvage value of steel.”
While the city reported estimated it would receive bids in the $950,000 range, instead the three bids made checked in at between $580,000 and $650,000.
The Vindicator describes the structure as a 78-foot steel girder structure that is in “poor condition.”
Latest from Construction & Demolition Recycling
- Evoquip adds trommel screen to product line
- Bomag to showcase innovations on the National Mall
- NWRA, SWANA to partner on safety, education and advocacy
- Caterpillar announces collision warning system, other technology for medium wheel loaders
- ABC: Nonresidential construction adds jobs in April despite headwinds
- Demolition underway at former SC steel mill
- Turkey neglects US scrap in favor of Russian shipments
- Results of New Hampshire waste study reveal missed opportunities for diversion